(Source: Eversheds LLP) Construction and engineering - Articles 15-10-2015 The recent case of Henia Investments Inc v Beck Interiors Ltd [2015] EWHC 2433 (TCC) emphasises the need for notices to be issued in strict compliance with the contract. Of particular interest are those parts of the judgement that relate to applications for interim payments. The Court stated that applications for interim payment must identify which contractual entitlement to interim payment (e.g. which monthly assessment date or milestone) it relates to. An application that the fails to do so will be invalid. The facts Henia Investments Inc ('the Employer') entered into an amended JCT Building Contract (2011 Without...
↧